Water Treatment Plant Project—75000m3/D
    发布时间: 2023-03-28 14:17    
Water Treatment Plant Project—75000m3/D

Background
The original treatment scale of the water treatment plant is 50,000 tons/day, and the treatment scale is 75,000 tons/day after the renovation. The original siphon filter tank was changed to submerged ultrafiltration membrane tank. The project is designed to save energy as the principle of siphon water production; the product model is US-45B; the designed average flux is 27LMH; the turbidity of the ex-factory water is less than 0.1NTU and COD is less than 0.2ppm. All the related indicators are far better than the national standard.

Project Overview
▪Capacity of Treatment: 75000m3/D                  
▪Type: Municipal Tap Water
▪Device: US-45B
▪Operating Flux: 27LMH